Question: Order Point = DDLT +SS DDLT= Demand During Lead time SS=Safety Stock Safety stock is one standard deviation and one standard deviation = 200 units.

Order Point = DDLT +SS DDLT= Demand During Lead time SS=Safety Stock Safety stock is one standard deviation and one standard deviation = 200 units. Calculate Order Point if DDLT is 1000 units. Also calculate order pint when safety stock is 2 standard deviation. What is the safety stock if Order point is 3000 and demand during demand during lead time is 2000 units
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock