Question: Orders finalized with weekly demand forecasts for the SCG0312 model of a bicycle manufacturer that manufactures its products in 330 pieces are shown in the

Orders finalized with weekly demand forecasts for

Orders finalized with weekly demand forecasts for the SCG0312 model of a bicycle manufacturer that manufactures its products in 330 pieces are shown in the table below. For the SCG0312 model, there are 230 products in stocks at the end of the 3rd period. Create the Master Production Schedule and calculate the quantities promised. Period Estimated Finalized Orders 4 120 80 5 130 150 6 130 100 7 150 200 8 150 140 9 160 60 10 180 20 11 180 30 12 120 0