Question: Oriole Enterprises Ltd . has entered into a contract beginning in February 2 0 2 3 to build two warehouses for Whispering Winds Structures Ltd
Oriole Enterprises Ltd has entered into a contract beginning in February to build two warehouses for Whispering Winds Structures Ltd The contract is a noncancellable fixedprice contract for $ million. The following data pertain to the construction period.
a
Costs for the year
$
Estimated costs to complete
Progress billings for the year nonrefundable
Cash collected for the year
Your answer is correct
Using the percentageofcompletion method, calculate the percentage complete for each year of the contract.
Calculate the amount of the gross profit to be recognized each year of the contract.