Question: ou are estimating your activity durations using Bottom-Up estimating. What does this mean? Select one: a. You are estimating the number of resources required for
ou are estimating your activity durations using Bottom-Up estimating. What does this mean?
Select one:
a.
You are estimating the number of resources required for each work package to increase the probability of being able to meet the estimated durations
b.
You are estimating the cost of each activity at the lowest possible level of detail
c.
You are performing decomposition on the deliverables to form Work Packages
d.
You are using detailed activity lists to assign individual activity durations so that they can be aggregated, while considering dependencies among activities