Question: Ouestion # 3 ( 2 0 Marks ) Use the following PERT diagram to answer the following questions How many possible paths are there from

Ouestion #3
(20 Marks)
Use the following PERT diagram to answer the following questions
How many possible paths are there from the start to the end of the project? List all possible paths.
Identify the tasks on the critical path, and the length of the critical path.
If task E took a day longer than planned, what effect if any would this have on the finishing date of the project?
If task D took 3 days longer than planned, what effect would this have on the finishing date of the project?
How many days over schedule could task A run without affecting the end date of the project?
What is this amount of time called?
(5+4+3+3+3+2)
 Ouestion #3 (20 Marks) Use the following PERT diagram to answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!