Question: OUESTION 3 The table below represents three point estimates for a project. Durations are measured in days: Calculate the missing values for the three -
OUESTION
The table below represents three point estimates for a project. Durations are measured in days:
Calculate the missing values for the threepoint estimate E the variance and
applicable totals.
Calculate the estimate for the project duration and the standard deviation
There is a need to find the probability that the project last longer than days.
Calculate the appropriate value and using the provided Table determine the
probability