Question: OUESTION 3 The table below represents three point estimates for a project. Durations are measured in days: Calculate the missing values for the three -

OUESTION 3
The table below represents three point estimates for a project. Durations are measured in days:
Calculate the missing values for the three-point estimate (E), the variance (V) and
applicable totals.
Calculate the estimate for the project duration and the standard deviation
There is a need to find the probability that the project last longer than 15 days.
Calculate the appropriate Z value and using the provided Z Table determine the
probability