Question: Over the last few weeks, the team has made three changes to the activities on the project. The project manager must be MOST careful to:
Over the last few weeks, the team has made three changes to the activities on the project. The project manager must be MOST careful to:
Record all the changes.
Prevent more changes from occurring.
Provide documentation on all the changes to the sponsor.
Make sure the changes are reflected in the project scope baseline.