Question: Overhead variance, missing information. Consider the following two situations- cases A and B- independently. Data refer to operations for April 2017. For each situation, assume
Overhead variance, missing information. Consider the following two situations- cases A and B- independently. Data refer to operations for April 2017. For each situation, assume standard costing. Also assume that use of a flexible budget for control of variable and fixed manufacturing overhead based on machine-hours.
| Case A | Case B | |
| 1. Fixed manufacturing overhead incured | $27,000 | $132,900 |
| 2. Variable manufacturing overhead incurred | $10,511 | ----- |
| 3. Denominator level machine-hours | ----- | 45,000 |
| 4. Standard machine-hours allowed for actual output achieved | 4,700 | ----- |
| 5. Fixed manufacturing overhead (per standard machine-hr) | ----- | ----- |
| Flexible-Budget Data: | ||
| 6. Variable manufacturing overhead (per standard machine-hr) | ----- | $210 |
| 7. Budgeted fixed manufacturing overhead | $23,375 | $103,500 |
| 8. Budgeted variable manufacturing overhead* | ----- | ----- |
| 9. Total budgeted manufacturing overhead* | ----- | ----- |
| Additional Data: | ||
| 10. Standard variable manufacturing overhead allocation | $10,340 | ----- |
| 11. Standard fixed manufacturing overhead allocation | $19,975 | ----- |
| 12. Production-volume vaiance | ----- | $580 F |
| 13. Variable manufacturing overhead spending variance | $ 457 U | $1,490 F |
| 14. Variable manufacturing overhead efficiency variance | ----- | $1,680 F |
| 15. Fixed manufacturing overhead spending variance | ----- | ----- |
| 16. Actual machine-hours used | ||
| *for standard machine-hrs allowed for actual output produced |
Fill in the blanks under each case. Fill in the knowns and then solve the unknows.