Question: P 2 ) Consider the same project specified in P 1 that requires 4 8 0 0 m 3 of sand, 5 8 0 0

P2) Consider the same project specified in P1 that requires 4800m3 of sand, 5800m3 of
fine gravel and 5700m3 of coarse gravel. You are now informed that two of the pits (Pit 3
and Pit 4) are out of commission due to safety violations, and you now have to get all your
material from Pits 1 and 2.
(a) Model the problem as a linear system of equations and write it in terms of
[A]{x}={B}
(b) Determine the volume of material that needs to be acquired from each of the two
pits to meet the project requirements using pseudo-inverses by hand (you are not
allowed to use MATLAB).
(c) Has the solution truly met the requirements of the project? If it has, is this solution
unique? If it has not, why not?
(d) What is the solution you get by using A??B in MATLAB? Does this solution truly meet
the requirements of the project? If it is different from the solution obtained in (b),
explain how this possible? Submit screenshots of command window
 P2) Consider the same project specified in P1 that requires 4800m3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!