Question: P 4 . ( 1 0 points ) A project consists of activities listed in the following table. Activity Immediate predecessor Optimistic Time ( Days

P4.(10 points) A project consists of activities listed in the following table.
Activity Immediate
predecessor
Optimistic
Time(Days)
Mostly likely
Time(Days)
Pessimistic
Time(Days)
A -567
B -6813
C -81318
D A 111420
E B 345
F C 7914
G E 4710
End D,F,G
a) Please indicate the critical path, based on the expected activity duration (forward and
backward pass analysis is not required).
b) Suppose the project will get a reward, if it is completed within 21 days. What is the
probability of getting the reward?