Question: P 4 . ( 1 0 points ) A project consists of activities listed in the following table. Activity Immediate predecessor Optimistic Time ( Days
P points A project consists of activities listed in the following table.
Activity Immediate
predecessor
Optimistic
TimeDays
Mostly likely
TimeDays
Pessimistic
TimeDays
A
B
C
D A
E B
F C
G E
End DFG
a Please indicate the critical path, based on the expected activity duration forward and
backward pass analysis is not required
b Suppose the project will get a reward, if it is completed within days. What is the
probability of getting the reward?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
