Question: Given the activities whose sequence is described by the following table: Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -- 3 5
Given the activities whose sequence is described by the following table:
| Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | -- | 3 | 5 | 13 |
| B | -- | 2 | 7 | 12 |
| C | A | 4 | 7 | 10 |
| D | B | 4 | 4 | 10 |
| E | C, D | 4 | 5 | 12 |
| F | B | 4 | 4 | 10 |
| G | E | 3 | 5 | 13 |
Using the appropriate PERT diagram:
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
