Question: Given the activities whose sequence is described by the following table: Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -- 3 5

Given the activities whose sequence is described by the following table:

Activity

Immediate Predecessor

Optimistic Time

Most Likely Time

Pessimistic Time

A

--

3

5

13

B

--

2

7

12

C

A

4

7

10

D

B

4

4

10

E

C, D

4

5

12

F

B

4

4

10

G

E

3

5

13

Using the appropriate PERT diagram:

- A. B. C. D. E. F.

Calculate the expected time for Activity D

- A. B. C. D. E. F.

What is the EF time for Activity F

- A. B. C. D. E. F.

What is the LS time for Activity D

- A. B. C. D. E. F.

Identify the critical path.

- A. B. C. D. E. F.

What is the expected project duration.

- A. B. C. D. E. F.

What is the probability that the project will be completed in 24 days or less?

A.

25 days

B.

0.36317

C.

12 days

D.

A-C-E-G

E.

8 days

F.

5 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!