Question: p . m . Fri 1 5 Mar 6 - Project Cost Management MCQ Time left 0 1 : 1 3 : 5 7 N

p.m. Fri 15 Mar
6-Project Cost Management MCQ
Time left 01:13:57
N.
c. Schedule
d. Float
Clear my choice
Question 3
Not yet a
Marked
A scheduled performance index of 0.76 means:
Select one:
a. You are only progressing at 76% of the rate originally planned.
b. You are ahead of schedule.
c. You are over budget.
d. You are only progressing at 24% of the ate originally planned.
Clear my choice
Question 4
Not y
Mark
Your project team is split between Limerick and Boston. Two of your team member the Boston site to pitch their final design idea to the rest of the team. The expense are an example of:
Select one:
a. Incrememntal costs
b. Direct costs
c. Fixed costs
 p.m. Fri 15 Mar 6-Project Cost Management MCQ Time left 01:13:57

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!