Question: P2. Based on the Table below, Activity ABCDEFGHI I (End) Immediate Predecessor 111 A A B B,C D E,F G, H, I Time (days)
P2. Based on the Table below, Activity ABCDEFGHI I (End) Immediate Predecessor 111 A A B B,C D E,F G, H, I Time (days) 8 20 33 18 20 9 10 8 4 a) Construct AOA and AON network diagrams. b) Perform the forward and backward pass analysis on the AON diagram. Indicate the critical path. c) What is the duration of the project? d) Calculate the total slack and free slack for all the non-critical activities.
Step by Step Solution
3.34 Rating (154 Votes )
There are 3 Steps involved in it
STEP BY STEP ANSWER AON DIAGRAM AOA DIAGRAM B Activity Immediate Predecessors Duration A 8 B 20 C 33 ... View full answer