Question: PA 9-6 For 120 consecutive days, a process engineer... For 137 consecutive days, a process engineer has measured the temperature of champagne bottles as they

PA 9-6 For 120 consecutive days, a process

PA 9-6 For 120 consecutive days, a process engineer... For 137 consecutive days, a process engineer has measured the temperature of champagne bottles as they are made ready for serving. Each day, she took a sample of 5 bottles. The average across all 685 bottles (137 days, 5 bottles per day) was 49 degrees Fahrenheit. The standard deviation across all bottles was 1.2 degrees Fahrenheit When constructing an X-bar chart, what would be the center line? degrees Fahrenheit

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts