Question: Paragraph A. Complete the table below by calculating the values for CV, CPL, SV, and SPI CV CPI SV SPI Tasks month 1 month 2

Paragraph A. Complete the table below by
Paragraph A. Complete the table below by calculating the values for CV, CPL, SV, and SPI CV CPI SV SPI Tasks month 1 month 2 month 3 month 4 month 5 EV $3,000 $9,000 $13,000 $2,500 $2,000 PY $3,500 $8,500 $12,000 $4,000 $2,000 AC $3,500 $8,000 $11,000 $3,500 $3,500 Earned Value Management formulas SV=EV-PV CVEEV-AC SPI-EV/PV CPI-EV/AC B. Determine the project status by evaluating CV, CPI, SV, and SPI for each month (eg. Over budget, on budget. Under budget etc) Cost Schedule Tasks month 1 month 2 month 3 month 4 month 5 C. Is the project successful? Why or why not

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!