Question: Part 1: ( See figure 1 part 1 below ). Calculate the ES, EF, LS, and LF times and the slack for each activity in
Part 1: (See figure 1 part 1 below). Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project, assuming must be done by 50 weeks (MUST SHOW WORK TO GET CREDIT INCLUDE FORMULAS). Can the project be completed in required completion time of 50 weeks? Why or why not? (25 points)
Figure 1- Part 1: Figure for Question 1 Part 1

EF=ES+ Estimated Duration LS = LF - Estimated Duration Required completion time =50 weeks =LF