Question: Question 2: 50 points total Part 1: ( See figure 2 part 1 below ). Calculate the ES, EF, LS, and LF times and the
Question 2: 50 points total
Part 1: (See figure 2 part 1 below). Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project (MUST SHOW WORK TO GET CREDIT INCLUDE FORMULAS). Can the project be completed in the required completion time of 38 weeks? Why or why not? (25 points)
Part 2: (See figure 2 part 2 below). Assume that Systems Analysis actually finished (duration) at 7 weeks, Design Input & Output actually finished (duration) at 3 weeks, and Develop Output Reports actually finished (duration) at 8 weeks. Can the project be completed in the required completion time of 38 weeks? Why or why not? (25 pts)

Part 1: Table for Part 1
| Activity # | Activity | ES | EF | LS | LF | Total Slack |
| 1 | Problem Definition | |||||
| 2 | System Analysis | |||||
| 3 | Design Input & Output | |||||
| 4 | Design Database | |||||
| 5 | Developer Input Screens | |||||
| 6 | Develop Output Reports | |||||
| 7 | Develop Database | |||||
| 8 | Test System | |||||
| 9 | Implement System |
EF=ES+ Estimated Duration
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
