Question: Part 1) See the table below for an activity network Current Preceeding Length (units) Activity 1 N/A 2 units Activity 2 Activity 1 4 units
Part 1) See the table below for an activity network
| Current | Preceeding | Length (units) |
| Activity 1 | N/A | 2 units |
| Activity 2 | Activity 1 | 4 units |
| Activity 3 | Activity 1 | 8 units |
| Activity 4 | Activity 1 | 6 units |
| Activity 5 | Activity 2 | 7 units |
| Activity 6 | Activity 4 | 4 units |
| Activity 7 | Activities 3, 5, 6 | 5 units |
Draw the network with the early/late starts/finishes and amount of slack per activity. Highlight the critical path as well.
Part 2) The activities in part 1 now have statistics associated with them. Activity 2, activity 3, and activity 7 now vary.
| Time (optimism) | Time (what will usually happen) | Time (pessimism) | |
| Activity 2 | 2 | 4 | 12 |
| Activity 3 | 2 | 8 | 10 |
| Activity 7 | 2 | 5 | 8 |
What is the chance that the critical path will be completed in the expected amount of time highlighted in part 1?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts