Question: Part 1 : Total productive maintenance, lean six sigma, SMED ( 1 2 points ) A company operates one 1 0 hours shift every day

Part1: Total productive maintenance, lean six sigma, SMED (12 points)
A company operates one 10 hours shift every day to produce 20,000 screws. Ideally, each serew takes 1 second of operations. During a regular production day, it has been reported that the machines have unscheduled down time of 45min and 500 screws do not match the required specifications. Given that a scheduled break of 45min and a setup time of 45min are assigned for each machine during each shift.
a) Calculate the Overall Equipment Effectiveness for the machines. (3 points)
b) Calculate the OEE if the setup time is reduced to 10min with no extra units prodaced. (3 points)
 Part1: Total productive maintenance, lean six sigma, SMED (12 points) A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!