Question: Part 2 : Determine the Process Cycle Efficiency ( PCE ) Now that Aidan has the PLT , he needs to understand what the current

Part 2: Determine the Process Cycle Efficiency (PCE)Now that Aidan has the PLT, he needs to understand what the current PCE is. With his team, he reviewed the swimlane and value stream maps that were created during the project and completed the following assessment for the amount of time spent doing something beneficial to the customer's requirements:- Design the system =.7 hours- Assemble the system =2 hours- Bench test the system =.5 hours- Program the system =3 hours- Validate the system =.4 hoursthe Process Lead Time (PLT) is 196.45 minutes per system.