Question: Part 2 : General Multiple Choice A project is ? a . Temporary b . Ongoing c . Unique d . Both A and C

Part 2: General Multiple Choice
A project is?
a. Temporary
b. Ongoing
c. Unique
d. Both A and C
A is a hierarchical decomposition of the project work scope into work packages that produce
the project deliverables.
a. Statement of work
b. Project scope document
c. Network diagram
d. Work breakdown structure
What range of CPI indicates that a project is currently experiencing a cost overrun (over budget).
a.CPI >1
b.CPI 1
c.CPI =1
d. None of the above
Earned Value, the value of
is a key parameter that must be determined throughout the
project.
a. The work scheduled
b. The resources used
c. The resources assigned
d. The work actually performed
A method for calculating the estimate at completion assumes that the work to be performed on the
remaining portion of the project or work package will be done at the same rate of efficiency as the work
performed so far. If the cost performance index is greater than 1.0, then:
a. The EAC is greater than the BAC
b. The EAC is less than the BAC
c. The FCAC cannot be calculated with the CPI
Which of the following is NOT an example of a risk response to a threat (negative impact):
a. Risk acceptance
b. Risk mitigation
c. Risk enhancement
d. Risk avoidance
 Part 2: General Multiple Choice A project is? a. Temporary b.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!