Question: Part 3 Resource Leveling (40 points) Using the data below (Assume normal workday = 8 hours/day & normal workweek = 40 hours/week) Work Hours Activity


Part 3 Resource Leveling (40 points) Using the data below (Assume normal workday = 8 hours/day & normal workweek = 40 hours/week) Work Hours Activity Immediate Duration in available ID Activity Predecessor days Resource per Day A Evaluate freezers 2 Alcides 6 B Chart temperatures 6 Joan 4 C Review service record 2 Alcides Consult with HVAC D engineer A, B, C 3 Alcides E Develop construction plan D 10 Joan F Complete IC assignment E 2 Alcides G Complete ROI analysis E 5 Joan H Conduct regulatory review E 4 Joan Obtain construction approval F, G, H 2 Alcides