Question: Part 3 Resource Leveling (40 points) Using the data below (Assume normal workday = 8 hours/day & normal workweek = 40 hours/week) Activity ID Activity
Part 3 Resource Leveling (40 points)
Using the data below (Assume normal workday = 8 hours/day & normal workweek = 40 hours/week)
| Activity ID | Activity | Immediate Predecessor | Duration in days | Resource | Work Hours available per Day |
| A | Evaluate freezers |
| 2 | Alcides | 6 |
| B | Chart temperatures |
| 6 | Joan | 4 |
| C | Review service record |
| 2 | Alcides |
|
| D | Consult with HVAC engineer | A, B, C | 3 | Alcides |
|
| E | Develop construction plan | D | 10 | Joan |
|
| F | Complete IC assignment | E | 2 | Alcides |
|
| G | Complete ROI analysis | E | 5 | Joan |
|
| H | Conduct regulatory review | E | 4 | Joan |
|
| I | Obtain construction approval | F, G, H | 2 | Alcides |
|
c. Joan and Alcides are not fully dedicated to the project. Joan is only available for 4 hours each day, and Alcides is available for 6 hours per day. The original estimated duration (in 8-hour days) results in over-allocation of Joan and Alcides. Prepare a resource-leveled project schedule in MS Excel. How long will it take to complete the project in a resource-leveled environment?
Please, do not copy and paste answers from the internet.
Please, answer fully for all the questions as described: Answer: Prepare a resource-leveled project schedule in MS Excel