Question: Part 3 : The following interior activities need to be completed before the new Oil Slick auto service store can be opened. The contractor is
Part :
The following interior activities need to be completed before the new Oil Slick auto service store
can be opened. The contractor is not sure when all the work will be done, but was able to come
up with the following estimates in days
Activity predecess
or
optimistic
time
most likely
time
pessimistic
time
A install floor
B paint A
C install signs B
D final
cleaning
C
If all these remaining activities are critical, what would be the expected completion time, in days,
of the remainder of the project? Path ABCD
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
