Question: Part 1 : Using the information given, a ) Calculate the completion time of the project. b ) Identify the activities on the critical path.

Part 1: Using the information given,
a) Calculate the completion time of the project.
b) Identify the activities on the critical path.
Activity Normal Time
(weeks)
A 4
B 3
C 5
D 2
E 5
F 6
G 4
H 3
Part 2: Using the table below, calculate the expected time for activity and the variance of estimated time for activity for activities A-B.
Activity
Optimistic Time Most Likely Time
Pessimistic Time
Expected Time
\sigma 2
A 138
B 245
Part 3:
The following interior activities need to be completed before the new Oil Slick auto service store can be opened. The contractor is not sure when all the work will be done, but was able to come up with the following estimates (in days).
Activity predecessor optimistic time most likely time pessimistic time
A (install floor)-----468
B (paint) A 151719
C (install signs) B 41220
D (final cleaning) C 6810
If all these remaining activities are critical, what would be the expected completion time, in days, of the remainder of the project? Path (A,B,C,D)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!