Question: Part 1 : Using the information given, a ) Calculate the completion time of the project. b ) Identify the activities on the critical path.
Part : Using the information given,
a Calculate the completion time of the project.
b Identify the activities on the critical path.
Activity Normal Time
weeks
A
B
C
D
E
F
G
H
Part : Using the table below, calculate the expected time for activity and the variance of estimated time for activity for activities AB
Activity
Optimistic Time Most Likely Time
Pessimistic Time
Expected Time
sigma
A
B
Part :
The following interior activities need to be completed before the new Oil Slick auto service store can be opened. The contractor is not sure when all the work will be done, but was able to come up with the following estimates in days
Activity predecessor optimistic time most likely time pessimistic time
A install floor
B paint A
C install signs B
D final cleaning C
If all these remaining activities are critical, what would be the expected completion time, in days, of the remainder of the project? Path ABCD
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
