Question: Part 3 Top management has accepted the schedule created at the end of Part 2. Prepare a brief memo that addresses the following questions: 1.


Part 3 Top management has accepted the schedule created at the end of Part 2. Prepare a brief memo that addresses the following questions: 1. How much will the project cost? What is the most expensive activity? The project will cost $810,309.62 total from analyzing the Gantt Chart and switching table to cost. The most expensive activity is 1.7 Detailed Product Design, with a cost of $215,451.92