Question: Part 4 . Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs in a schedule is 1 st ,2 nd
Part 4. Questions 6,7. [ Use Video-1 under Scheduling heading. ]
[Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.]
The jobs A,B,C,D,E, arrived in that order to be processed on two machines.
| Job | A | B | C | D | E |
| Time on Machine 1 | 48 | 56 | 66 | 34 | 78 |
| Time on Machine 2 | 45 | 68 | 64 | 56 | 80 |
|
Question 6. Which is the Johnsons Rule schedule? (A) ACEBD (B) DBECA (C) DCABE (D) DABEC (E) none of the above
|
|
Question 7. Consider the FIFO schedule of (A,B,C,D,E). How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The total time of completion is 362 Statement 2. The flow time of job D is 292 Statement 3. The total queue time of job C is 106 Statement 4. The total idle time of machine 2 is 59 . . . |