Consider the jobs scheduled on two machines in the order of (A,B,C) where each job is started as soon as possible. The processing times for each job on each machine are given in the table below. Assume time on machine #1 is represented with (1) and on machine #2 with (2).

Job

Machine#1 Time

Machine#2 Time

A

2

1

B

3

2

C

1

3

Question 8. Which Gantt chart is correct for the schedule (A,B,C)?

Gantt Chart A

Job

T1

T2

1

2

3

4

5

6

7

8

9

10

11

12

A

2

1

(1)

(1)

(2)

B

3

2

(1)

(1)

(1)

(2)

(2)

C

1

3

(1)

(2)

(2)

(2)

Gantt Chart B

Job

T1

T2

1

2

3

4

5

6

7

8

9

10

11

12

A

2

1

(1)

(1)

(2)

B

3

2

(1)

(1)

(1)

(2)

(2)

C

1

3

(1)

(2)

(2)

(2)

Gantt Chart C

Job

T1

T2

1

2

3

4

5

6

7

8

9

10

11

12

A

2

1

(1)

(1)

(2)

B

3

2

(1)

(1)

(1)

(2)

(2)

C

1

3

(1)

(2)

(2)

(2)

Gantt Chart D

Job

T1

T2

1

2

3

4

5

6

7

8

9

10

11

12

A

2

1

(1)

(1)

(2)

B

3

2

(1)

(1)

(1)

(2)

(2)

C

1

3

(1)

(2)

(2)

(2)

E

E. None of the above

. . .

Question 9. How many of the statements are correct for the schedule (A,B,C)?

(A) 0 (B) 1 (C) 2 (D) 3 (E) 4

Statement 1. The total processing time of the schedule is 10

Statement 2. The total queue time of job C is 6

Statement 3. The total flow time of job B is 7

Statement 4. The total idle time of machine 2 is 4

. . .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!