Question: Part 5: CLO 5 Question 1 David, the project manager, is now working on procurement planning for the project. He is looking at the following
Part 5: CLO 5
Question 1
David, the project manager, is now working on procurement planning for the project. He is looking at the following options for procuring different pieces. Advice the right procurement contract option for the following situation (justify your answer):
- David will pay $3,000 for the use of a facility and $5,000 per month for the consulting team and engineering, working on the acquired part for the duration of the project. However, there is a limit of $50,000 for the maximum cost.
- David will pay the labor cost each month plus 5% of this cost as food at work and for recognition and rewards for the labor.