Question: Part A is made from 2 Part Cs and 2 Part Ds . The lead time for each item is 1 week. The batch size

Part A is made from 2 Part Cs and 2 Part Ds. The lead time for each item is 1 week. The batch size for Assembly A is LFL. Part C is made in lots of 60. Part D is made in lots of 120. Prepare a release schedule for Part C based on the information. Your answer is complete showing the release schedule by week for Part C. No other information is required

ITEM:Assembly A

LFL Order Amt

0

1

2

3

4

Gross Requirements

50

50

50

125

On Hand

150

ITEM: Part C (2 per)

Lot size 60

0

1

2

3

4

Gross Requirements

On Hand

150

ITEM: Part D (2 per)

Lot size 120

0

1

2

3

4

Gross Requirements

On Hand

200

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!