Question: Part A of this problem is correct, can someone help with explaining and solving part B? A project for improving a billing process has the

Part A of this problem is correct, can someone

Part A of this problem is correct, can someone help with explaining and solving part B?

A project for improving a billing process has the following precedence relationships and activity times Activity Immediate Predecessors) s Activity Time (weeks) 5 9 9 C D E F G G H B, C B 11 9 5 E F G 7 a. Choose the correct network diagram below. a S S B a @ D S B 19 b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack [weeks) A 5 B 9 C E 9 F 5 G 8 H