Question: Part A- The normal time for the complete operation= minutes Part B- The standard time for the process= minutes Peter Rourke,
Part A- The normal time for the complete operation= " " minutes
Peter Rourke, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table 1 Task Element 1 2 3 Performance Rating 110% 90% 85% 80% 0.4 0.5 0.6 1.5 Observation (minutes per cycle) 2 3 4 03 0.7 0.3 0.9 0.6 0.7 0.5 0.8 0.4 1.7 1.9 1.6 5 0.5 0.6 0.6 14 The allowances for tasks such as this are personal, 6%; fatigue, 8% and delay, 4% a) The normal time for the completo operation minutes (round your response to wo decimal places)
Part B- The standard time for the process= " " minutes