Question: Part a . Using the survey data below, complete the table ( all HI's for the TP points, all elevations ) and perform the arithmetic

Part a.
Using the survey data below, complete the table (all HI's for the TP points, all elevations) and perform the arithmetic check. (16 points)
Example entry: 9.20(nearest hundredth, no zeros before single digits)
\table[[Station,BS,HI,,IS,FS,Elevation,],[BM 42,2.71,,,,,,],[TP 1,3.62,,,,,,]]
Arithmetic check:
Part b.
Plot the profile points (Sta ,0+00-5 ta,3+00) on your graphing paper at a scale of 1''=40' horizontally and 1''=2' vertically (see Figure 4.15 in your Kavanaugh text for reference). Label the x and y axes. (10 points) Uplond your work with your question #7 work
Part a . Using the survey data below, complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!