Question: Part B : Case Study (60 marks) Using the information in the table below to answer Question 1 and Question 2. Task Predecessors Duration A

Part B : Case Study (60 marks) Using the information in the table below to answer Question 1 and Question 2. Task Predecessors Duration A 5d A 3d B c D B 5d B 6d E C,D 4d Marks Question 1 (10 marks) Please finish the following Gantt chart using information above, and then list the critical path. A A B D ITI + 15 Un 10 + 20 Gantt chart
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts