Question: 1 5d 2 60 Part B: Case Study (60 marks) Marks Question 1 (15 marks) ID Task name Duration Predecessors 1 Obtain Authorization 10d 2
1 5d 2 60 Part B: Case Study (60 marks) Marks Question 1 (15 marks) ID Task name Duration Predecessors 1 Obtain Authorization 10d 2 Hire Analyst 15d 3 Plan training 2 4 Arrange Logistics 20d 5 Announce training 3,4 Using the information in the table above draw a Gantt chart and PERT chart of the project to determine the earliest completion time for the project and identify the critical path for the project. You must submit: a) GANTT chart b) PERT chart c) Earliest Completion Time of the project d) Critical Path Note: Please finish the PERT chart using the format as below. Task name Start day: ID: Finish day: Dur