Question: part b is correct i just need help with part c. calculating the slack for each activity? b. Determine the critical path and project duration.

b. Determine the critical path and project duration. The erical path is path and the project duration is 28 days. (Enter your rosponse as an integer.) c. Calculate the slack for each activity. (Enfor your responses as integers.) The following information is known about a projoct to upgrade a point-of-sale system at Kids and Tots Appare: a. Choose the correct network diagram for this project