Question: part C calculate the slack for each activity. b. Determine the critical path and project duration. The critcal path is path A.C.D.E.G and the project
b. Determine the critical path and project duration. The critcal path is path A.C.D.E.G and the project duration is 28 days. (Enter your response as an integer) c. Calculate the slack for each actevity. (Enter your responses as integers.)