Question: Part I A recycling facility processes 100 MT a day in a 10 hour shift It uses 2 recycling lines 10 people Calculate the hourly
| Part I | |||||
| A recycling facility processes 100 MT a day in a 10 hour shift | |||||
| It uses | |||||
| 2 recycling lines | |||||
| 10 people | |||||
| Calculate the hourly productivity in lbs | |||||
| Per line | |||||
| Per worker | |||||
| Conversion | 1 MT = | 2204.6 lb | |||