Question: Part III- Problems (15 Points): 7. (7.5 points) For the schedule shown below: a. Draw the activity on node diagram. b. Perform the CPM calculation.

Part III- Problems (15 Points): 7. (7.5 points)

Part III- Problems (15 Points): 7. (7.5 points) For the schedule shown below: a. Draw the activity on node diagram. b. Perform the CPM calculation. C. Calculate the forward and backward pass and total floats (slacks). Activity Predecessor Duration A 4 B A B D 7 6 11 8 10 E F B, C B, C D, E, F EF GH G 7 8 H 1 6