Question: Part Three: Forecast Project Cost Answer the following questions, using as much space as you need. Refer back to the sample project examined in module

 Part Three: Forecast Project Cost Answer the following questions, using as

Part Three: Forecast Project Cost Answer the following questions, using as much space as you need. Refer back to the sample project examined in module two and imagine that everything is executed perfectly. Imagine that you have just now come to the end of time period 16. Activity 4-5 is now complete as scheduled, and Activity 3-6 has also just completed, two periods ahead of schedule. Imagine that Resource A cost $6,000 for each period it was active on Activity 3-6: 5 periods, not the 7 periods at $5,000 per period expected. You are now ahead. In answering the questions below. remember that Resource A has a planned cost of $5,000 per period of use. and Resource B has a planned cost of $3,000 per period of use. 1' Resource Type w 0113156?.Dn121814$WiwnliliIQHlil'l-N\" Jan 16 Sept 16 Nov 16 Dec 16 Jan I? my 17 July 17 Aug 17 Aprll 18 Using the methods presented in this module, answer the following questions. 1. What is the cost variance? 2. What is the new forecasted total cost at completion if you use Method 1? USING EARNED VALUE 3. What is the new forecasted total cost at completion if you use Method 2? USING CPI

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!