Question: Part Three: Forecast Project Cost Answer the following questions, using as much space as you need. Refer back to the sample project examined in the
Part Three:
Forecast Project Cost
Answer the following questions, using as much space as you need.
Refer back to the sample project examined in the project, part two, and imagine that everything is executed perfectly. You have now reached the end of time period Activity is completed as scheduled, and Activity is also finished, two periods ahead of schedule. Resource A was expected to cost $ per period for periods. However, the actual cost was $ per period for periods. This means you are now ahead. In answering the questions below, remember that Resource A has a planned cost of $ per period of use, and Resource B has a planned cost of $ per period of use.
What is the cost variance?
$k
What is the new forecasted total cost at completion if you use Method
Positive cost variance indicates that the project is underbudget.
Hence the new forecasted total cost at completion will be $ less than the old forecasted total cost at completion.
$k
What is the new forecasted total cost at completion if you use Method
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
