Question: Part Three: Forecast Project Cost Answer the following questions, using as much space as you need. Refer back to the sample project examined in the

Part Three:
Forecast Project Cost
Answer the following questions, using as much space as you need.
Refer back to the sample project examined in the project, part two, and imagine that everything is executed perfectly. You have now reached the end of time period 16. Activity 4-5 is completed as scheduled, and Activity 3-6 is also finished, two periods ahead of schedule. Resource A was expected to cost $5,000 per period for 7 periods. However, the actual cost was $6,000 per period for 5 periods. This means you are now ahead. In answering the questions below, remember that Resource A has a planned cost of $5,000 per period of use, and Resource B has a planned cost of $3,000 per period of use.
1. What is the cost variance?
$5k
2. What is the new forecasted total cost at completion if you use Method 1?
Positive cost variance indicates that the project is underbudget.
Hence the new forecasted total cost at completion will be $5000 less than the old forecasted total cost at completion.
= $30k
3. What is the new forecasted total cost at completion if you use Method 2?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!