Question: Part Two: Using Critical Project Management Tools Answer the following questions about the project network below, using as much space as you need. 1 .
Part Two:
Using Critical Project Management Tools
Answer the following questions about the project network below, using as much space as you need.
Map the earliest start times for each activity to the resource demands over time. What are the earliest start times for each activity?
Create a leftjustified schedule for the project above
Assuming you have five people available with similar skills level the schedule so it is consistent with resource availabilities. What is the new project duration?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
