Path A-B-E has a 70% probability of being

Path A-B-E has a 70% probability of being completed within 3 weeks. Path C-D-F has a 95% probability of being completed within 3 weeks. If these are the only two paths in a project network, what is the probability the project will be completed in 3 weeks? a. 95.096 b.87.5% c. 70.0% d. 66.5% Oe: 25.0%