Question: A project has two paths that you are concerned about. The first path (which we will call #1) has an expected path time of 15
- A project has two paths that you are concerned about. The first path (which we will call #1) has an expected path time of 15 weeks and a standard deviation of 3. The second path (#2) has an expected path time of 14 weeks and a standard deviation of 3.4. Which path is critical if the project must be completed within 17.5 weeks?
| Path #2 with a probability of approximately 85% | ||||||||||||||||||||
| Path #2 with a probability of approximately 75% | ||||||||||||||||||||
| Path #1 with a probability of approximately .83 | ||||||||||||||||||||
| Path #1 with a probability of approximately 80% | ||||||||||||||||||||
| Path #2 with a probability of approximately 1.03 | ||||||||||||||||||||
| Path #1 with a probability of approximately 90%
|