Question: path should also be determined. Here are the activity times: table [ [ Activity , Time ( weeks ) Immediate Predecessor ( s )

path should also be determined. Here are the activity times:
\table[[Activity,Time (weeks) Immediate Predecessor(s),Activity,Time (weeks) Immediate Predecessor(s),,],[A,5,-,E,5,B],[B,8,-,F,6,B],[C,2,A,G,10,C, E],[D,2,A,H,7,D, F]]
Dave's earliest start (ES) and earliest finish (EF) are:
\table[[Activity,ES,EF],[A,0,5],[B,0,8],[C,5,7],[D,5,7],[E,8,13],[F,8,14],[G,13,23],[H,14,21]]
Dave's latest start (LS) and latest finish (LF) are:
\table[[Activity,LS,LF],[H,16,23],[G,13,23],[F,10,16],[E,8,13],[D,14,16],[C,11,13],[B,0,8],[A,6,11]]
The slack times are:
ActivitySlackA6B0C
 path should also be determined. Here are the activity times: \table[[Activity,Time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!