Question: Path What is the probability of completing path 1-4-6-7 between 26 and 29 days using the following project information? Path Path Duration Standard Deviation 1-2-5-7

Path What is the probability of completing path

Path What is the probability of completing path 1-4-6-7 between 26 and 29 days using the following project information? Path Path Duration Standard Deviation 1-2-5-7 24 days 2.236 days 1-3-7 22 days 1.414 days 1-4-6-7 25 days 2.000 days Select one: O a. 0.4332 O b. some other value O c.0.4772 O d. 0.9330 O e. 0.2857