Question: People are served in a process with two resources. The first resource has a capacity of 1 . 4 people per minute. The capacity of

People are served in a process with two resources. The first resource has a capacity of 1.4 people per minute. The capacity of the second resource is 1.2 people per minute. Demand for this process is 1.4 people per minute.
What is the cycle time of this process (in seconds)?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.