Question: People are served in a process with two resources. The first resource has a capacity of 1.4 people per minute. The capacity of the second

 People are served in a process with two resources. The first

People are served in a process with two resources. The first resource has a capacity of 1.4 people per minute. The capacity of the second resource is 12 people per minute. The first resource has 3 workers and the second resource has 5 workers. One additional worker is hired who is as productive as the current workers Instruction: Round your answer to three decimal places What is the new capacity of this process? people per minute