Question: Per PMI, what are the three processes that comprise planning for and acquiring project resources? A Estimate activity resources, budget resources, acquire resources B Plan
Per PMI, what are the three processes that comprise planning for and acquiring project resources?
A Estimate activity resources, budget resources, acquire resources
B Plan resource management, estimate activity resources, procure resources
C Plan resource management, estimate activity resources, acquire resources
D Plan resource management, estimate activity resources, interviewresources