Question: Perform a financial analysis for a project. Assume that the projected costs and benefits for this project are spread over four years as follows: Estimated
Perform a financial analysis for a project. Assume that the projected costs and benefits for this project are spread over four years as follows: Estimated costs are $300,000 in Year 1 and $30,000 each year in Years 2, 3, and 4. Estimated benefits are $0 in Year 1 and $120,000 each year in Years 2, 3, and 4. Use a 9 percent discount rate, and round the discount factors to two decimal places. What is the total discounted cost? (Keep your answer in two decimal places. e.g. 446929.98. Do not enter \$ symbol.)